Drawing abbreviations are short forms for repeated instructions: 4X means a callout applies to four features, TYP means typical, THRU means all the way through, and REF means reference only. When you balloon a drawing each one decides how many rows the callout produces.
Detail A · The abbreviations

Reading table

Abbreviation Means What to do in a report
4X (or any N X) The callout applies to that many features One balloon with N results, or split into sub-numbers
TYP Typical: the same applies to similar features Confirm how many features it covers; ask if unclear
THRU The hole goes all the way through Record as part of the requirement; check the feature goes through
REF Reference value, information only Normally not inspected
MAX / MIN The value is an upper or lower limit Record the limit; result must not pass it
DIA or the diameter sign Diameter Part of the requirement text
R Radius Part of the requirement text
SQ Square Part of the requirement text
CSK / CBORE Countersink / counterbore See hole callouts
DP Depth Part of the requirement text
Detail B · 4X

What does 4X mean on a drawing?

4X means the callout applies to four features. Example: "4X diameter 9.0 plus or minus 0.1 THRU" is four holes. Record it as one balloon with four results, or split it into 6.1 to 6.4 so each hole has its own result, as the tool does with its split-quantity action.

TYP

TYP means typical. It says one dimension stands for several like features. Inspectors must confirm how many features it covers, because the drawing does not always say.

THRU

THRU means the feature passes entirely through the part. In "diameter 9.0 THRU" there is no depth to measure, but the hole must break out the far side.

Common mistakes

  • Measuring one hole when the callout covers four.
  • Treating TYP as a count.

More abbreviations, with an example each

The table below goes beyond the first ones. The meanings are common drafting usage, written in our own words: the drawing's own notes and the standard it cites govern, and where an abbreviation could mean two things, ask.

Abbreviation Meaning Example on a drawing Effect on the report
B.C. Bolt circle: the circle on which a hole pattern lies 90.0 B.C. One characteristic for the circle diameter; the holes are separate
BSC or BASIC Basic size, a theoretically exact value 25.00 BSC No plus-minus; judge the governing frame
REF Reference value, for information 50.0 REF Normally not balloon-worthy
TYP Typical: applies to similar features R3 TYP Confirm the count of features
EQ SP Equally spaced 6X EQ SP Spacing is part of the requirement
4X, 6X Quantity prefix 4X 9.0 THRU One balloon, several results
THRU Passes completely through 9.0 THRU Check it breaks through
DP Depth 6 DP A separate measurement
CBORE Counterbore CBORE 11 DP 6.5 Diameter and depth
CSK Countersink CSK 90 deg Diameter and angle
SQ Square SQ 12 Both sides
DIA Diameter, written out DIA 30 Same as the diameter symbol
R Radius R3 Check with a radius gauge
MAX, MIN Upper or lower limit 0.8 MAX One-sided limit; result must not pass it
NTS Not to scale NTS under a view Do not scale from it
SF or Ra Surface finish Ra 1.6 Profilometer reading
C/L Centre line C/L Reference for symmetry
MMC, LMC Maximum, least material condition circled M Bonus tolerance may apply
UNO Unless otherwise specified UNO 0.5 R Applies where nothing else is stated
ALL OVER Applies to every surface 0.4 ALL OVER One note, many surfaces

Worked example on the sample part

The sample's hole callout is 4X diameter 9.0 plus or minus 0.1 THRU. Reading the abbreviations: 4X gives four holes, THRU says each passes right through. The tool balloons it once, as balloon 6, with limits 8.9 to 9.1. With split quantity turned on it becomes 6.1 to 6.4, one result per hole. The bolt circle callout 90.0 B.C. is balloon 7, and it is a separate characteristic from the holes.

Reading a callout from left to right

A line such as "4X diameter 9.0 plus or minus 0.1 THRU" reads: quantity, symbol, size, tolerance, instruction. Each piece answers a question. How many, what shape, how big, how accurate, how deep. When a callout adds a counterbore, repeat the same questions for it.

Mistakes inspectors make

  • Counting TYP features from the view the callout is in, and missing identical features in other views. Confirm with the drawing owner.
  • Treating B.C. as a tolerance and not a location.
  • Measuring a MAX value as if it were a nominal with a plus-minus.
  • Reading EQ SP as optional: equally spaced is a requirement, and the spacing needs a result.
What does 4X mean on a drawing?
The callout applies to four features.
What does TYP mean on an engineering drawing?
Typical: the same applies to similar features. Confirm how many.
What does THRU mean on a drawing?
The hole passes all the way through.
How do I record a 4X dimension?
See the 4X section above.
What does B.C. mean on an engineering drawing?
B.C. means bolt circle, the circle on which a pattern of holes lies. The diameter printed with it is the diameter of that circle, and it is a separate characteristic from the hole sizes. Measure and record both, as separate balloons.
What does UNO mean on a drawing?
UNO means unless otherwise specified. A note such as UNO 0.5 R says every radius takes that value except where the drawing gives another. Treat it as a requirement for each such feature, and balloon those features that carry no value of their own.